Thursday, November 3, 2016

Heating and cooling updates

Work on the utility project. 

From Chad Sweatman, Manager, Building Support Services: 

  • The cool building temps we’ve had the past few weeks have been fixed. The radiant hot water system is now back online. Work has begun replacing the chilled water system. It will be offline for three weeks.
  • There will be a steam outage starting tomorrow morning (November 4)  through Sunday (November 5). There will be no heat or hot water during this time. Workers will be completing work on the utility project in the parking lot. This will provide some relief from the hot building temps if we can hang in through today. The forecasted lows and cooler weather next week should help the situation going forward.
  • Work continues on the elevators. Both should be back in service at the end of the month.
  • The grad addition continues to track on schedule.   
The front of the building on November 3.


No comments:

Post a Comment

Thanks for your comment or question--you will see it appear on the blog shortly.